On the basis of the Environmental and Social Impact
Assessment (ESIA) carried out
in October 2006 and the environmental monitoring being
carried out by BPA the following key impacts have been
identified;
Inundation of landmass up to 444 km2 at Full
Supply Level
Resettlement of 1,216 people in Project area
Pollution
Air Emission, dust from vehicular movement
Noise and Vibration from rock blast
Water
Soil erosion and land degradation
Construction activities on the river bed, sand excavation
and construction of the main dam
Direct loss and/or disturbance of vegetation from;
Socioeconomic Issues
Pressure on social amenities such as clinics, schools,
toilets, boreholes
Impacts from influx of workers
Social upheavals due to greater economic strength of workers
Impoundment of the reservoir |