Project Implementation

The Government of Ghana has entered into an Engineering Procurement and Construction (EPC)/Turnkey Project Contract with SINOHYDRO Corporation Limited, a major Chinese dam construction firm of international repute.

Project Implementation Schedule
The key elements of the project schedule are summarized below:

   Commencement of preliminary stage – May 2007

   Commencement of preparatory stage – August 2007

   Construction of basic infrastructure e.g. roads, camps, etc – November 2007

   River Closure – December 2008

   Commissioning of 1st Unit – October 2012

   Completion and Commissioning of project – February 2013