Project Milestones and Completion Schedule

 

PHASE I (Actual)

Activity

October 2007

Commenced Field Investigations

January 2008

Commenced Preparatory Works

December 2008

River Diversion Completed

PHASE II (Actual)

 

January November 2009

River bed excavation & foundation

December 2009

Commenced Main RCC Dam

June 2011

Commencement of Reservoir Filling

PHASE II (Expected)

 

Second Quarter of 2013

Completion and Commissioning of Project

 

 

 
 
 