Project Milestones
and Completion Schedule |
|
|
PHASE I (Actual) |
Activity |
|
October 2007 |
Commenced Field Investigations |
|
January 2008 |
Commenced Preparatory Works |
|
December 2008 |
River Diversion Completed |
|
PHASE II (Actual) |
|
|
January – November 2009 |
River bed excavation & foundation |
|
December 2009 |
Commenced Main RCC Dam |
|
PHASE II (Expected) |
|
|
First Quarter of 2011 |
Start of Reservoir Filling |
|
Fourth Quarter of 2012 |
Commissioning of First Unit |
|
Second Quarter of 2013 |
Completion of Project |
|
|
|
|
|
|
|