Bui Project Timelines

 
 
 

Project Milestones and Completion Schedule

 

PHASE I (Actual)

Activity

October 2007

Commenced Field Investigations

January 2008

Commenced Preparatory Works

December 2008

River Diversion Completed

PHASE II (Actual)

 

January – November 2009

River bed excavation & foundation

December 2009

Commenced Main RCC Dam

PHASE II (Expected)

 

First Quarter of 2011

Start of Reservoir Filling

Fourth Quarter of 2012

Commissioning of First Unit

Second Quarter of 2013

Completion of Project

 

 
 